Major Road & Drainage Improvements

Project Name Status Contract Price Contractor Notice to Proceed Projected Completion Date Project Files
Airport Road to Hwy 11 Connector  ROW  $10,000,000.00 estimate  All south      Airport Rd. to Hwy 11 Connector  
Allen Road  In Progress  $239,559.00  Barrier Construction  05/02/2008  09/02/2008  Allen Road Project  
Arrowwood Pond Weir Replacement Project  In Progress          Arrowwood Pond Weir Replacement  
Bayou Castine Headwater Improvements  Planned for 2008          Bayou Castine Headwaters Improvement  
Bayou Castine Headwater Study  In Progress          Bayou Castine Headwaters Study  
Black River Detention  Construction          Black River Detention Project  
Brewster Rd.  Under Construction- Estimated Completion May 2008  $1,548,021.98  Cov Paving      Brewster Road  
Brownswitch @ Military  Design  1.5 M estimate  Atlas      Brownswitch @ Military Road  
Chinchuba ACQ, Phase 1  Design/ROW          Chinchuba Acquisition  
Claiborne Hill Overpass- Hwy 190 @ Bogue Falaya Bridge  Design  TBD  KLL      Claiborne Hill Bridge  
Cloverland Acres  Planning          Cloverland Acres Area  
Commercial Square Dr.  Design          Commercial Square Drive  
Covington By-Pass South (Hwy. 21 to Hwy. 1085)  Design  1.3M estimate  Richard Lambert      Covington Bypass South  
Covington By-Pass North (Hwy. 190 to Hwy. 25)  Design  TBD        Covington Bypass North  
Cypress Park  Construction          Cypress Park  
Emerald Forest Extension  Design/ROW          Emerlad Forest  
Falconer Dr. Extension (Concrete Roadway)  Bid Acceptance on April 14. Work to begin mid June.  $1,738,670.70  Stranco      Falconer Drive  
French Branch/ Meadowlake            French Branch/Meadowlake Project  
Haas Road Pond & Pumping Station  Project to be rebid in May          Haas Rd. Pumping Station Haas Rd. Pond  
Haas Rd. Widening  ROW    Burkes      Haas Road Widening  
Holly Dr. Guard Rail  Project Completed  $33,600.00  Traffic Solutions Inc.    04/23/2008  Holly Drive  
Hwy 11 @ I-12 Interchange  ROW  3M estimate  BKI      Hwy. 11 @ I-12  
Hwy 21 @ I-12 (Phase 3)  Design  10M estimate  Richard Lambert      Hwy. 21 @ I-12  
Hwy 21 (Oschner to Bootlegger) Interchange Improvements  ROW  7M estimated  Richard Lambert      Highway 21 Improvements  
Hwy 22 Widening (ph 1)  Under Construction- Estimated Completion May 2008  $3,055,550.00  Boh Bros      Hwy. 22 Widening  
Hwy 25 @ US 190  Design  2 M estimate  Bonura & Boruka      Hwy. 25 @ US 190  
1077 Widening Part A (I-12 to 1085)  ROW  2M estimate  Atlas      Hwy. 1077 Widening  
1077 @ US 190  Design  2 M estimate  PEEC      1077 Widening @ Hwy 190  
1077 Widening Part C (1085/1077 Intersection Improvements)  ROW  10M estimate        1077 Widening  
1085 Widening  Design    NY Assoc.      Hwy. 1085 Widening  
Huntwyck Village Drainage  Design          Huntwyck Village Drainage  
I-12/59 Improvements  Design  3.7 M estimate  Buckhort Horn      I-12 @ Hwy. 59 Improvements  
I-12/1077 Intersection  Project Complete  $1,155,817.40  Barriere      I-12 @ 1077 Improvements  
I-12 Ski Pond  Land Acquisition          I-12 Ski Pond  
I-12 / Tchefuncte Interchange  Under construction  $9,700,000.00  Richard C. Price      Aerial Photo Project Area  
I-59 @ Military Road  Design  2.5M estimate        I-59 @ Military  
Lacombe Pedestrian Bridge  Under Construction- Completion anticipated for late June 2008  $1,942,476.00  McDonald      Lacombe Pedestrian Bridge  
Lacombe Park & Ride  Under Construction- Completion anticipated for late May 2008  $887,151.10  Stranco      Lacombe Park and Ride  
Little Bayou Castine Headwater Study  In Progress          Little Bayou Castine Study  
North Bayou Liberty Detention  Land Selection/Acquisition          North Bayou Liberty Detention  
Northshore Hospital Pond  Design/ROW/Construction          Northshore Hospital Pond  
Nunez Rd.- road repair from hurricane damage  Bid Under Review          Nunez Road Project  
Parc du Lac Weir - shared 3 ways  Planned for 2008          Parc du Lac Weir Project  
Robert Blvd. @ Brownswitch  Design  1.5 M estimate  Atlas      Robert Road @ Brownswitch  
Robert Rd. Area Drainage Study  In Progress          Robert Road Drainage Study  
SELA Study            SELA Study  
Tammany Hills  Land Acquisition          Tammany Hills Drainage Improvements  
Timber Branch Pond Bulkhead Construction  Planned for 2008          Timber Branch Pond Project  
Tolawa            TOLOWA Project  
Viola Rd.  Out to Bid          Viola Road  
Woodlands Drainage  Land Acquisition          Woodlands Drainage  

Key Description
Design Project is in the planning/design stage and may include determining project needs, logistical determinations, cost estimates etc.
Design/Row Project is in the design phase and the design is being determined by the Right of way needs.
Out to bid/ Bid under review Project is in the bid process whereby the Parish is awaiting/or evaluating bid proposals from prospective vendors on the subject project. 
ROW Determining and/or acquiring Right of way for project area.
Under Construction Project is in the construction process.