Major Road & Drainage Improvements

Project Name Status Contract Price Contractor / Consultant Notice to Proceed Projected Completion Date Project Files
Allen Road  Complete  $239,559.00  Barriere Construction  05/02/2008  09/02/2008  Allen Road Project  
Arrowwood Pond Weir Replacement Project  Design/Planning          Arrowwood Pond Weir Replacement  
Bayou Castine Headwater Improvements  Planned for 2009          Bayou Castine Headwaters Improvement  
Bayou Castine Headwater Study  In Progress          Bayou Castine Headwaters Study  
Black River Detention  Design          Black River Detention Project  
Chinchuba ACQ, Phase 1  Design/ROW          Chinchuba Acquisition  
Cloverland Acres  Planning/Design          Cloverland Acres Area  
Covington By-Pass South (Hwy. 21 to Hwy. 1085)  Design  1.3M estimate  Richard Lambert      Covington Bypass South  
Commercial Square Dr.  Design    Department of Engineering      Commercial Square Drive  
Covington By-Pass North (Hwy. 190 to Hwy. 25)  Design  TBD        Covington Bypass North  
Cypress Park  Planning/Design          Cypress Park  
Emerald Forest Extension  ROW/Permitting- On Hold    RCL      Emerlad Forest  
Falconer Dr. Extension (Concrete Roadway)  In Progress  $1,738,670.70  Stranco  06/09/2008  06/12/2009  Falconer Drive  
Fitzgerald Church Road Bridge  Project Complete  $11,649.97  Sandridge  02/25/2009  04/24/2009   
French Branch/ Meadowlake- Drainage Analysis Study  Study Complete  $250,000.00  Kyle & Associates    07/31/2008  French Branch/Meadowlake Project  
Guste Island Road  Project Complete  $19,150.00  RJ Booty       
Haas Road Pond & Pumping Station  Under Construction  $2,058,430.00  Great Southern Dredging  10/09/2008  06/12/2009  Haas Rd. Pumping Station Haas Rd. Pond  
Haas Rd. Widening  ROW    Sean Burkes      Haas Road Widening  
Holly Dr. Guard Rail  Project Completed  $33,600.00  Traffic Solutions Inc.    04/23/2008  Holly Drive  
Hwy 21 @ I-12 (Phase 3)  Design  10M estimate  Richard Lambert      Hwy. 21 @ I-12  
Hwy 21 (Oschner to Bootlegger) Interchange Improvements  Under Construction  $8,775141.40  Gilmore & Sons  08/04/2008  09/14/2009  Highway 21 Improvements  
Hwy 22 Widening (ph 1)  Project Complete  $3,055,550.00  Boh Bros      Hwy. 22 Widening  
Hwy 25 @ US 190  Design  2 M estimate  Bonura & Boruka      Hwy. 25 @ US 190  
1085 Widening  Design  $760,000.00  NY Assoc.      Hwy. 1085 Widening  
Huntwyck Village Drainage  Design  $5,000,000.00  Digital Engineering      Huntwyck Village Drainage  
Koop Drive Extension  Bid Under Review  $1.2 Million est  RCL       
I-12/1077 Intersection  Project Complete  $1,155,817.40  Barriere      I-12 @ 1077 Improvements  
I-12 / Tchefuncte Interchange  Project Complete  $9,703,595.59  Richard C. Price  03/17/2008  03/17/2009  Aerial Photo Project Area  
I-59 @ Military Road  Design  2.5M estimate  Buchart Horn      I-59 @ Military  
Lacombe Pedestrian Bridge  Project Complete  $1,942,476.00  McDonald  10/22/2007    Lacombe Pedestrian Bridge  
Lacombe Park & Ride  Project Complete  $887,151.10  Stranco  09/04/2007  05/27/2008  Lacombe Park and Ride  
Lacombe Trailhead  Design Review    STP Engineering       
Lakeshore Blvd. East Widening  Under Construction  $901,654.59  Byron Talbot  04/28/2009  08/26/2009   
Little Bayou Castine Headwater Study  In Progress          Little Bayou Castine Study  
North Bayou Liberty Detention  Land Selection/Acquisition          North Bayou Liberty Detention  
Northshore Hospital Pond  Design/Planning          Northshore Hospital Pond  
Nunez Rd.- road repair from hurricane damage  Project Complete  $93,252.00  Boh Bros.  03/12/2008  04/26/2008  Nunez Road Project  
Parc du Lac Weir  Engineering Design/Analysis          Parc du Lac Weir Project  
Pearl Acres Widening  Design  $1,608,000.00  Aims       
Robert Blvd. @ Brownswitch  Design  $750,000.00  Atlas      Robert Road @ Brownswitch  
Robert Rd. Area Drainage Study  In Progress          Robert Road Drainage Study  
Tammany Hills  Land Acquisition          Tammany Hills Drainage Improvements  
Timber Branch Pond Bulkhead Construction  Planned for 2009          Timber Branch Pond Project  
Tolawa  Land Acquisition          TOLOWA Project  
Viola Rd.  Project Complete  $1,685.995.00  Barriere  06/03/2008  10/31/2008  Viola Road  
Woodlands Drainage  In Progress- Excavation          Woodlands Drainage  

Key Description
Design Project is in the planning/design stage and may include determining project needs, logistical determinations, cost estimates etc.
Design/Row Project is in the design phase and the design is being determined by the Right of way needs.
Out to bid/ Bid under review Project is in the bid process whereby the Parish is awaiting/or evaluating bid proposals from prospective vendors on the subject project. 
ROW Determining and/or acquiring Right of way for project area.
Under Construction Project is in the construction process.