Project Name Status Contract Price Contractor Consultant Notice to Proceed Projected Completion Date Project Files
Road Projects
Airport Road Connector - Phase 1  Under Construction  $2,569,795.00  Barriere  Allsouth  04/23/2012  01/28/2013   
Airport Road Connector - Phase 2A Clearing and Grubbing  Under Construction  $383,000.00  Stranco Inc.  Allsouth  05/08/2012  09/05/2012   
Airport Road Connector - Phase 2B  Design  TBD  TBD  Allsouth       
Brownswitch Road Widening  Planning  TBD  TBD  TBD       
East Howze Beach Road - Raising  Under Construction  $320,748.00  Stranco Inc.  STP  08/27/2012  01/24/2013   
Frances Rd @ Bootlegger  Bidding Process  $1,325,000.00  TBD  NY & Associates       
Huntwyck Village Drainage Improvements - Phase 2  ROW Acquisition  TBD  TBD  Digital Design       
Huntwyck Village Drainage Improvements - Phase 1  Under Construction  $2,673,950.00  Fleming  Digital Design  05/01/2012  12/17/2012  Huntwyck Village Drainage  
Hwy 59 @ LA 1088 Turn Lane  Under Construction  $246,047.65  Stranco Inc.  Kelly McHugh  07/09/2012  10/09/2012   
LA 59 @ Sharp Rd.  Design  TBD  TBD  RCL       
LA 59 @Lonesome Rd.  Design  TBD  TBD  Bucart Horn       
Project Icebox (84 Lumber Rd Connector/OMR Turn Lane)  Under Construction  $1,376,881.00  Leon Lowe  JV Burkes  07/09/2011  10/23/2012   
Project Icebox (Military @ Cleo)  Bidding Process  $1,150,000.00  TBD  JV Burkes       
Drainage Projects
Hwy 434 Retention Lake  Design  $361,538.75  Allsouth  TBD       
Hidden Oaks Lane Drainage  Design  $120,000.00  TBD  JV Burkes       
Lapin St. Pond Phase 1  Design  TBD  TBD  STP       
Meadowlake Pond Improvements  Under Construction  $732,464.05  Kort's Trucking  DDG  07/12/2012  01/18/2013   
Raymond Rd. Drainage  Design  $135,000.00  TBD  STP       
Schneider Canal Pump Station Improvements  Design  TBD  TBD  GEC       
South Slidell Levee Segment 3A  Planning  TBD  TBD  STP       
South Slidell Levee 4  Design  TBD  TBD  GEC       
Timber Branch Pond  Under Construction  $176,873.00  Stranco Inc.  WINK  04/09/2012  08/10/2012  Timber Branch Pond Project  
DOTD Projects
Airport Rd - I-10 (I-12 Widening)  Under Construction  $25,664,489.16  James Construction Group  DOTD  03/01/2011  07/01/2012   
I-10 SW Frontage Road Extension  Under Construction  $2,989,156.75  Boh Bros  DOTD  02/24/2011  11/30/2011   
Robert Blvd. @ Brownswitch  Under Construction  $1,010,393.33  RCS Contractors, Inc.  Atlas  07/19/2010  08/07/2012  Robert Road @ Brownswitch  
Roundabout @ East JCT LA 434  Out to Bid  $500,000 - 1M  TBD  DOTD       
Miscellaneous Projects
Cypress Bayou Intermediate Detention Pond  Under Construction  $2,857,690.24  Durr Heavy Construction  CDM  01/26/2012  01/20/2013   
Cloverland Rd Proposed Canal  Bid Review  $627,332.00  TBD  STP       
Cypress Park Drainage Improvements  Design  $1,556,021.00  TBD  TBD       
Hwy 190 @ Bogue Falaya Bridge  Design Only  $86,975.00  TBD  Kyle & Associates       
Hwy 41 Park & Ride  Design  $300,000.00  TBD  PEEC, Inc.       
Internal French Branch Improvements  Contract Review  $1,170,000.00  TBD  TBD       
Labarre Street Detention Pond & Drainage Improvements  Under Construction  $711,133.22  Advanced Quality Construction  Bucart Horn       
Lower W-15 Area Drainage Improvements  Design  $9,400,000.00  TBD  Duplantis       
Little Bayou Castine Headwater Improvements  Design  $638,420.00  TBD  STP       
St. Tammany Parish Airport: Taxiway Extension & Hanger Apron Phase 2  Contract Review  $1,400,000.00  Advanced Quality Construction  PEC       
Completed Projects
Covington Bypass South (Hwy 21 to Bootlegger)  Complete  $3,128,577.92  Amtek  Richard C. Lambert  04/26/2010  02/13/2012  Covington Bypass Project Location  
Fishing Pier  Complete  $485,000.00  Gill's Crane  STP  08/18/2011  02/06/2012   
Holiday Square Blvd Turn Lane  Complete  $124,002.15  Fleming  STP  02/20/2012  06/20/2012   
Krental Rd @ Hwy 434 & Fishery Hatchery  Complete  $350,549.13  Huey Stockstill  STP  08/10/2011  12/29/2011   
Koop Drive Extention East  Complete  $284,573.55  Leon Lowe  RCL  06/30/2011  09/01/2012   
Lowe Pond Canal Erosion  Complete  $534,000.00  ERS Incorporated  STP  09/26/2011  03/26/2012   
Schneider Canal Back Flow Protection  Complete  $275,884.00  McDonald Construction, Inc. of Slidell  RCLC  03/06/2012  08/07/2012   
Ski Pond Rd (Ben Thomes Rd)  Complete  $20,089.00  Nick's Dozer  JV Burkes  10/03/2011  04/30/2012   
Voters Rd @ LA 433 Improvements  Complete  $283,904.34  Kass Brothers  Principle  09/12/2011  02/23/2012   

Project maps will be added as they become available.

Key Description
Design Project is in the planning/design stage and may include determining project needs, logistical determinations, cost estimates etc.
Design/Row Project is in the design phase and the design is being determined by the Right of way needs.
Out to bid/ Bid under review Project is in the bid process whereby the Parish is awaiting/or evaluating bid proposals from prospective vendors on the subject project. 
ROW Determining and/or acquiring Right of way for project area.
Under Construction Project is in the construction process.